Following the success of the Advanced Engineering Centre in Bedford Ashe Construction Ltd rewarded us with a further project for the MEP installation at their new SEAT Motor Dealership In Letchworth . With the overall build valued at £2m, CCC undertook the design and build of the MEP in a package valued at £300k. Works were undertaken in a 15 week programme with excellent progress made by the CCC team who had installed showroom lighting prior to the curtain glazing being installed. The excellent progress made by CCC helped the contractors site team focus their efforts, where it was needed, on other parts of their supply chain. The project was completed on programme with a delighted end client and contractor. The project is now in the throes of the final fit out by SEAT.